PROGRESS OF THE WORK ABOUT HUANCABAMBA

THE FIRST MODULE

Mounting collar beam ties the perimeter of the building. It consists of two pieces of wood joined by screw studs.


now really starting to look a little house!

restrooms

thrilled roofing ago, the custom is to throw a party but we opted for a football game!

Enjoying the view!
Although I have not yet developed the ability of workers to walk on the ceiling. Always throw a few laughs when they see me up and move with little skill, but I'm getting better!


SECOND MODULE



THE LAYOUT AND THE EXCAVATION OF TRENCHES
Following the same procedure as above, with a width of 60cm by 90cm deep.




EMPTYING PHASE OF
All the equipment we turn it


formwork OVERLOAD AND ARMED WITH THE CANES

a team photo



The rate of entry was frantic, a team of about 8 people and within a week we were up.