MULTIPURPOSE HALL
Coating:
For facing the same criteria used in other modules, sand and cement mortar in proportion 1:4. To do this follow the following process:
- Installation of connectors that tie both sides of the mesh. Connectors for use galvanized # 8 and fills the hole with cement to prevent rusting.
- Placement of welded mesh, galvanized 3 / 4 "tin nailed with nails.
- Nailing connectors.
- Rear without finishing with cement mortar. In a first phase, the breeches with gravel that is allowed to dry a couple of days before giving a smooth finish with fine sand.
Floors:
VERY COLORFUL!
start with the interior floor. Being a large area is divided into 8 panels that give an ocher-colored finish. Follow the same procedure as in the other modules:
- A compacted layer of 10cm said.
- A layer 5cm gravel.
- A 5cm flooring available on the grid of rods 1 / 4 ".
- The finished floor about 10cm.
Here is mounting. we emptied two pieces per day nonconsecutive order stripping the boards the next day.
Sidewalks:follow the same approach as in the interior. The path allows us to protect the perimeter perimeter of the building and give a slight tilt to the outside to prevent the accumulation of water. Also divided in colorful cloths separated by an expansion joint.
------------ perimeter formwork the rain
Preparing -------- finish --- Well colorful!
ocher + cement
In the last stage without finishing and apartments, all did everything and we all learned. In the photo at the bottom that you know, teaching those who are learning. most important and the main thing that we get this project is the formative work as a school where we all learned.